Features of UP Solar Policy

1) Will remain in operation till 31st March 2017
2) Project Size – Min 5 MW
3) Sale options
a) Discoms (Developers selected through competitive bidding)
b) Third Party Sale (Subsidy or GBI not available)
4) PPA of 10 years
5) Time limit of commissioning for solar PV – 13 months
6) Solar power plant of 5 MW and above can be built for captive use
No comments are provided on cross-subsidy charges in the policy