Uttarakhand released RFP for 30 MW and 50 MW solar plants under type 1 and type2 catagory

Posted · Add Comment

[ezcol_1half]Government of Uttarakhand has released two RFPs of 30 MW (SPV) and 50 MW (SPV/ ST) for solar power on 20 – Aug -2014 under its Solar Power Policy – 2013 which aims to set 500 MW by the year 2017. There is 30 MW RFP for solar Photovoltaic (SPV) plant under category I, which comprises competitive bidding process for solar plants to sell power to Uttarakhand DISCOM for meeting RPO Obligation as specified by UERC from time to time, and another 50 MW for solar thermal/ solar PV (ST/ SPV) under category II, which comprises Projects set up on private land for captive use or sale of power to 3rd party within or outside the state or project setup on private land under Renewable Energy Certificate (REC) Mode.For the RFP of 30 MW for solar PV the Minimum capacity of a solar plant shall be 100 kW and maximum capacity can be 30 MW. Successful bidder can setup plant anywhere in the state.

RFP provides some benefits to the project developers like

  • If the developer purchase private land for the project, than they will be eligible for an exemption of 50% on stamp duty.
  • In case Developer is using the agriculture land for establishing Solar power plant then he would be exempted from paying any conversion rate

Bidders are required to quote a levelized tariff for 25 year and PPA shall be done for the same period. Project developer have to maintain minimum 19% of CUF. Bidders shall be responsible to get the grid connectivity. Transmission line shall be constructed by STU/DISCOM but the cost will be borne by project developer.  Projects has to be connected at 33/11 kV system.

The time schedule for the bid process is –

S. No. Event Tentative Schedule
1 Date of RFP Zero Date (20/08/2014
2 Submission of written clarification/ amendment in RFP document Zero Date + 10 days
3 Pre Bid Meeting Zero Date + 20 days
4 Revision of RFP and RFP documents and issuance of revised RFP Zero Date + 40 days
5 Last date of submission of Bid Zero Date + 61 Days
6 Scrutiny of the Non-financial Bid and publication of shortlisted bidders on UREDA website Zero Date + 73 Days
7 Financial Bid Opening Zero Date + 76 Days
8 Approval of Bids and issue of LOI to Successful Bidder Zero Date + 107 Days
9 Submission of contract performance guarantee (CPG) by Successful bidders as per Clause 2.19 Zero Date + 122 Days
10 Issuance of project allotment letter and signing of PPA Zero Date + 137 Days
11 Completion of the following task:
a. Financial closure of the project.
b. Land Allotment/ purchase.
c. Grant for Grid Connectivity.
LOI date + 240 Days
12 Commissioning of solar PV power plant LOI Date+ 570 Days (Project allotment date +540 days

[/ezcol_1half] [ezcol_1half_end]

last date of bid submission is 20.10.2014 before 12:00 hours (IST).

For the RFP of 50 MW for solar ST/ SPV the Minimum capacity of a solar plant shall be 100 kW and maximum capacity can be 50 MW. In this also successful bidder can setup plant anywhere in the state. The benefits for project developers for this RFP is also the same.

Qualification criteria for bidder:

  • bidder needs to have net worth of 3 Cr/ MW at least seven days prior to date of submission
  • bidder needs to demonstrate its technical ability and to do so bidder can have technology tie-up

The schedule for the bid process is –

S. No. Event Tentative Schedule
1 Date of issue of RFP
Last date for submission of proposal
Zero Date (20/08/2014)
2 Last date for submission of proposal Zero Date + 47 Days
3 Scrutiny of the proposals and publication of shortlisted developers on UREDA website Zero Date + 60 Days
4 Publication of list of developers as approved by project approval committee Zero Date + 75 Days
5 Issuance of LOA to successful developer for security deposit in the form of Bank Guarantee Zero Date + 82 Days
6 Issuance of project allotment letter PAL
Zero Date + 90 Days
7 Submission of land proposal papers PAL + 180 Days
8 Financial closure of the project PAL + 270 Days
9 Commissioning of Solar PV power plant PAL + 540 Days
(for PV)
PAL + 900 Days
(for ST)

The last date of bid submission is 07.10.2014 before 12:00 hours (IST).

The wheeling charges shall be applicable as decided by UERC, and if open Access is granted to any developer or beneficiary they shall have to pay the applicable Open Access charges and losses as approved by UERC from time to time. However, the Cross Subsidy Surcharge shall not be applicable for Open Access obtained for third party sale within the state.

RFPs can be downloaded from here

RFP_30MW_SPV

RFP_50MW_ST/SPV

[/ezcol_1half_end]