  • PEDA is coming up with Rfp for new grid connected solar photo voltaic power projects 250 MW capacity
  • There are 3 categories for the project :
  1. Category 1 : Minimum is 1 MW and Maximum is 4 MW and the total capacity is of 50 MW and with the multiples of 1 MW only
  2. Category 2 : Minimum is 5 MW and Maximum is 24 MW and the total capacity is 100 MW and the multiples of 5 MW only
  3. Category 3 : Minimum is 25 MW and Maximum is 50 MW and the total capacity is 100 MW and the multiples of 5 MW only. A bidder can also set up 2 projects of 25 MW under 50 MW capacity
  • Only 1 project shall be allocated to a bidder
  • The project would be allocated to the new incorporated / existing companies
  • The PPA shall be executed between PSPCL and the selected bidder within 30 days from the signing of implementation agreement. PPA shall be valid for 25 years from the date of commissioning of complete plant or partial capacity.
  • Date of sale of e- Bid document 24th December 2015 at 10:00 AM
  • Date of pre-bid meeting is on 9th January 2015 at 12 PM
  • Last date of submission of e-Bid is on 28th January 2015 at 12 PM
  • Date and time of opening of technical e-Bids is on 30th January 2015 at 12:30 PM

Read more : http://www.peda.gov.in/tenders/PressNotice_1.pdf

Read more : http://www.peda.gov.in/tenders/TenderDnit_1.pdf

 