Charges payable for the Open Access on Transmission and Distribution System in Rajasthan: 2015-16

Posted · Add Comment

Charges payable for the Open Access on Transmission and Distribution System in Rajasthan: 2015-16

 

 

RVPN

Transmission Charges:                                                             Rs. 138.10/kW/month Transmission Charges (For STOA customers):                                                                                           Rs.4.54/kW/day Transmission Charges (For interstate bilateral &

collective power exchange transactions):                                                                                                   29.23 paisa/kWh

(As per final tariff approved for FY 2015-16 vide order dated 14.08.2015 by the RERC)

 

Transmission Losses:                                                                                                  4.15%

(Approved for FY 2015-16vide order dated 14.08.2015 by the RERC)

 

SLDC

Operation Charges:                                                                      Rs. 1.13/kW/month

(As per final tariff approved for FY 2015-16 vide order dated 14.08.2015 by the RERC)

 

Scheduling Charges:

For generators above 10 MW:                                                        Rs. 50000/schedule if daily schedule is not submitted

 

For generators above 1 MW:                                                           Rs. 5000/schedule if weekly schedule is not submitted

 

For OA consumers:                                                                   Rs. 1000/schedule

if daily schedule is not submitted

 

Discoms

Wheeling Charges:

EHV                                                                                                        1 p/kWh

33 kV                                                                                                    11 p/kWh

11 kV                                                                                                    32 p/kWh

 

Losses:

 

System Voltage System losses
33 kV 3.80%
11 kV 12.60%

 

(As per System Losses approved by RERC vide order Dated :8th August, 2012)

 

Surcharge (Applicable for OA consumers having third party sale):

 

 

Category

LIP-

EHV

LIP-

33 kV

LIP-

11 kV

ML-

EHV

ML-

33 kV

ML-

11 kV

NDS-

EHV

NDS-

33 kV

NDS-

11 kV

Surcharge

(Rs./kWh)

 

0.18

 

0.13

 

0.05

 

0.15

 

0.09

 

0.02

 

0.49

 

0.43

 

0.36

 

(As per System Losses approved by RERC vide order Dated: 31th March, 2011)

Transmission and other charges