Overall Status of tendering/PPA’s for commissioning of solar projects in 2016-17

Posted · Add Comment

With GOI Support

Sl.

No.

Tendering by Tendering

Capacity (MW)

Remarks Expected

commissionin g in 2016- 17(MW)

1 SECI 2670 Under 2000 MW VGF Scheme

a)  Gujarat- 225 MW(Open)+25 MW(DCR)

b)  Maharashtra- 450 MW(Open)+50 MW(DCR) )(Bids of 450 MW

opened)

c)  UP- 440 MW(open)

d) AP- 500 MW(02-01-16)

 

Total= 1690 MW tendered

1600
1250 1250 MW Under 5000 MW VGF

Scheme of MNRE to be tendered by Jan 2016 subject to Cabinet Approval

1000
100 100 MW Project allotted and Under

Canal-top/ bank scheme of MNRE.

 

Total=64 MW tendered.

44
62.5 62.5 MW SECI’s own projects

 

Total=10MW tendered

50
3 3 MW IPTPS, New Delhi, LOI issued

on 07.10.2015

Total= 3MW tendered.

3
2 NTPC Ltd.

( Developer mode)

3000 Under 3000 MW Bundling Scheme of

MNRE

a)     AP Solar park 50×10 = 500 MW (29-4-15), reverse acution- 03.11.2015, Entire capacity won by Sun Edison at Rs 4.63/kWh

b)    Rajasthan Solar Park 70×6= 420 MW (21-5-15),Technical Bid Open, Reverse auction-18/01/2016 Rs 4.34/kWh,4.35/kWh, 4.36/kWh

c)     AP Solar Park 350 MW single project – reverse acution- 14.12.2015, Entire capacity won by SB Cleantech at Rs 4.63/kWh 50×3 = 150 MW (DCR category) (21-5-15) Reverse acution- 15/12/2015, Rs 5.12/kWh&5.13

d)    Rajasthan  130 MW(open)+100 MW(DCR) =230 MW(21-05-

2000

State Govt Supported projects

S.No State Tendering Capacity Remark Expected commissioning in 2016-17 (MW)
1 Punjab 500 MW Financial Bid opened on

07-09-2015. LOI issued on 19.10.2015 and PPA

of 350 MW is signed and rest is under process.

500
2 Karnataka 300 MW Under Farmer scheme,

PPA signed

 

 

 

1000

1200 MW Request for proposal

(RFP) invited on 20.11.2015. Technical Bid opened.

3 Madhya

Pradesh

300 MW Financial Bids opened on

15.07.2015. PPA signed

300
4 Telangana 2000 MW Financial Bids opened on

03.08.2015. LOI issued.

2000
5 Haryana 150 MW Technical Bid opened.

Financial Bid opened on 07.12.2015. LOI issued.

150
6 Uttar Pradesh 215 MW LOI issued on

09.09.2015 and PPA

signed.

223
7 Uttrakhand 170 MW Financial Bids opened on

28.10.2015. LOI issued and process of signing of PPA.

191
8 Andhra

Pradesh

500 MW Tender issued by

APGENCO on EPC

basis. Technical bid opened on 30.11.2015. Under process of awarding the projects.

200
9 Tamil Nadu 1284 MW Under Preferential Tariff,

PPA signed of 1284 MW

700
10 Jharkhand 1200 MW Tender issued by JREDA

on 07.12.2015

200
  Total 7819 MW   5464 MW