100 KW Solar Rooftop project at Ratan textiles

FGC has selected to install 100kWp solar rooftop system. First Green is providing various services including project management service and Engineering, Procurement, Construction (EPC) & commissioning. The project has started with roof survey to estimate the capacity. Team took various parameters such as wind speed, wind direction, global horizontal solar radiation, shadow analysis, available roof top area. Based on these analysis/parameters team prepared Project design, Drawings and documents for electrical works, Drawings and documents for plant Civil Works, Structure, foundation , strategic solar plant layout, team decide to select non penetrable installation on roof top.