Project Case Study scheme for petrol pump solarisation
With the massive target of the SolarIsation of petrol pumps, Indian Oil has recently launched a subsidy program for which Firstgreen Consulting is a empannelled EPC partner to IOCL. Under the proposed scheme consumer has to pay only 35% if the project cost and balance 65% is paid to the beneficiary petrol pump owner by IOCL as subsidy for the solar PV system.
The proposed scheme is for 3KW/5KW/7KW/10 KW/15 kW solar PV systems for grid connected as well as for off grid applications. The p;roposed system will consist of poly crystalline solar modules arranged in series and parallel combination meeting PCU/Inverter voltage and current requirement.
The DC output from the solar Panels is fed to a hybrid inverter or a grid connected inverter, which is synchronized with the LT panel and the electricity is fed to the system. In case of a hybrid system the electricity generated by the solar plant is fed to the loads as well as stored in the batteries. The batteries act as a power back up source in the event of power outages. This not only reduces the electricity bills but also reduces the diesel consumption. The solarisation of petrol pumps is not only environmentally beneficial, but also increases sales of the petrol pump retail outlets.
IOCL SUBSIDY SCHEME
Table1: Off grid system (with batteries)
System capacity in kWp | Cost of Solar Panel (in Rs) | Inverter capacity in kVA | Cost of Inverter and Battery (in Rs) | Total cost of the system | % subsidy proposed for different capacity | Celling of subsidy (in RS) rounded off |
3 | 160000 | 5 | 175000 | 335000 | 55 | 185000 |
5 | 260000 | 5 | 175000 | 435000 | 60 | 260000 |
7 | 365000 | 10 | 265000 | 630000 | 60 | 380000 |
10 | 510000 | 10 | 265000 | 775000 | 65 | 500000 |
15 | 760000 | 15 | 400000 | 1160000 | 65 | 755000 |
Table2: On- grid system (without batteries)
System capacity in kWp | Cost of Solar Panel (in Rs) | Inverter capacity in kVA | Cost of Inverter (in Rs) | Total cost of the system | % subsidy proposed for different capacity | Celling of subsidy (in RS) rounded off |
3 | 160000 | 5 | 87500 | 247500 | 55 | 135000 |
5 | 260000 | 5 | 87500 | 347500 | 60 | 210000 |
7 | 365000 | 10 | 132500 | 497500 | 60 | 300000 |
10 | 510000 | 10 | 132500 | 642500 | 65 | 420000 |
15 | 760000 | 15 | 200000 | 960000 | 65 | 625000 |
PV Module Type | Poly Crystalline |
Tilt Angle | As per Site |
Inverters | String Inverters |
Project Completion Time | 1-2 Months |
Table 4: Bill of Quantity
S.No. | Component | Specification | Make |
1 | Modules-320Wp | As per Design | Vikram Solar/Sova Solar |
2 | Inverters | As per Design | Delta/INVT/Sungrow for On-grid system
Statcon/Sukam/equivalent for Off-grid systems |
5. | AC & DC Cables | As per Design | Siechem Technologies, Polycab, LAPP or equivalant |
8. | ACDB | As per Design | As per Firstgreen design |
9. | Earthing | As per Design | Traditional |
10. | Cable Tray | As per Design | Armored Firstgreen vendor |
Note: – Cable Length and BOS mentioned above are used as per actual site conditions. This BOQ may be used for reference but actual BOQ may differ as per the detailed engineering.
Scope of Work
- Design, Engineering, Procurement &Supply of Solar power system as per specification & BOM given in our offer.
- Installation & Commissioning of Solar Power Plant up to LT Panel including synchronization with Grid supply.
- Supply of Solar Meter, Net Meter are in the scope of supplier while all fees and deposits and electrical components required for Net Metering would be paid by customer
- Providing after-sales service during the warranty period.